See below for more detailed information on our ongoing paving projects, including a timeline for the work and phasing maps for the work near you.
Milliken Avenue Project
Project Timeline
- October 1: Finalize sidewalk and curb ramp work
- October 2 - 25: Pavement and striping work. Intermittent lane closures but driveway access will be maintained.